Project management of a DNV-certified hose reel unit
Compliance: DNV 2.7-1 / 2.7-3 (offshore frames)
Phase: Fabrication, testing and logistics
Scope: Project management and client-witnessed delivery
The challenge: offshore requirements on every part
We were responsible for the full project coordination of a custom-built hose reel system in a DNV-certified lifting frame. The complexity was not only in the mechanics of the reel, but in the strict offshore requirements for the frame and the assembly. Fabrication, certification and client acceptance had to fit together seamlessly.

The milestone: Factory Acceptance Test
The critical moment was the Factory Acceptance Test (FAT). The client flew in to the workshop for it. Before the visit we wrote a detailed FAT procedure and submitted it to the client for approval, so the test had an agreed basis.

On the test day we were the central point of contact and demonstrated the function and safety of the unit step by step against the protocol. Thanks to that preparation, the test ran efficiently and transparently.
The result: successful delivery
After the FAT we drew up the punch list together with the client, coordinated the follow-up and made sure every item was closed out correctly and on time. After final sign-off, the unit was prepared for transport and shipped to the client's project location.

What this project shows
- Client and stakeholder management: guiding clients through critical phases such as a FAT, so they gain confidence in the delivery.
- Quality assurance and procedures: no ad-hoc testing, but an approved procedure as the contractual basis for acceptance.
- Punch list management and close-out: a project is only finished when the punch list is empty and the documentation is complete.
- Compliance control (DNV): making sure the end product meets the certification requirements for offshore frames.